Rapid-Deployment Aseptic Injectables Suite

A factory-integrated PAC suite delivered additional sterile filling capacity while the client’s existing facility remained in operation.

Rapid-Deployment Aseptic Injectables Suite
2000m² Controlled area
22 weeks Delivery
ISO 8 Cleanroom class
01
THE CHALLENGE

Working Around Real Project Constraints

The client needed new aseptic capacity on a compressed schedule, with minimal construction activity beside a live GMP production area and a clear path through qualification.

02
THE SOLUTION

Engineered for the Process

Wonclean engineered a pre-assembled suite with integrated air handling, HEPA filtration, pressure cascade controls, utilities and environmental monitoring. Factory acceptance testing was completed before the modules were shipped and connected on site.

SCOPE OF DELIVERY

A Coordinated Cleanroom Package

The project package was coordinated as a complete system, keeping architectural, mechanical and controls interfaces aligned from design through qualification.

  • 01Modular cleanroom envelope
  • 02Integrated HVAC and HEPA filtration
  • 03Pressure cascade and BMS controls
  • 04FAT, SAT and qualification support